7.    Commencement and Completion of Construction.    Unless the following time periods are expressly extended by the Developer in writing, construction of the residence on a Lot shall be commenced within three months following the date of delivery of a deed from the Developer to the purchaser of such Lot and shall be completed within seven months after such construction commencement. In the event such construction is not commenced within such three month period (or extension thereof if any), the Developer shall have, prior to commencement of construction, the right (but not the obligation) to repurchase such Lot from the Owner at the sale price of the Lot from the Developer to the initial purchaser thereof. If such repurchase right is exercised by the Developer, the Owner of the Lot in violation of this construction commencement provision shall not be entitled to reimbursement for taxes, interest or other expenses paid or incurred by or for such Owner.